Local Success Stories |
|
|
Country |
Italy |
Download pdf version
Download pdf version part II
|
# |
Name of Example |
Location |
1 |
District Heating plant Ferrara |
Ferrara |
|
The Initiative |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
The District Heating plant in Ferrara is an integrated system of geothermal, waste incineration and reserve boilers. The system mainly uses the heat energy coming from the geothermal fluid extracted from the subsoil by means of two wells. The secondary source is depicted by the waste-to-energy plant, and another tertiary source of production is a thermal plant made up of 7 natural gas-powered boilers to produce hot water. The production system is composed by:
At the end of the 1960s, an underground hot water basin was found, deep 2.000m in Casaglia. After 1970s energy crisis, the Joint Venture AGIP-ENEL made up the Geothermal Project, to use the geothermal basin for district heating. Geothermal fluid is pumped towards the surface through two wells. The fluid releases energy to the district heating network through a heat exchanger, and finally re-injected in the underground through an intake well. Today, with a water flow of 400 m3/h (at a temperature of 100°C), geothermal source contributes with 14MWt of the total power required. The waste-to-energy plant in Ferrara is located inside the site called "geothermal power", where the district heating plant of the city of Ferrara is also situated. In operation since 1993 with a 150 t/day capacity treatment line, the plant attains heat recovery generated in the waste incineration process for the combined production of electricity and heat. Based on the season and needs, a part of the steam can be bled from the turbine to transfer energy to the adjacent district heating plant through a dedicated heat exchanger. The waste-to-energy plant is being upgraded and redeveloped, and today is in the final completion stage. Two new waste-to-energy lines are planned in its final configuration. The two new lines have been in the start-up stage since November 2007.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
A. TECHNOLOGY
1. Waste receiving, storage and feed section The plant has two ditches ( a main and an auxiliary) for storing incoming waste. Total usable capacity is 5000 m3 to allow the furnaces to operate normally and with a continuous infeed, even if there are consecutive days without any receipt of waste. Two orange-peel buckets on a bridge crane run alternatively inside the building housing the main ditch, one as stand-by to the other, to perform the waste homogenizing functions in the ditch and to load them into the furnace hopper.
The combustion chamber is the moving grate type with a water cooling system, able to treat waste with a calorific value ranging from 6700 to 16,750 kJ/kg. To achieve utmost flexibility, the system supplying the material onto the grate is fitted with a double feed-pusher. The material is transported onto the grate by a sloping chute, also water-cooled. The slope of the grate is 14 degrees, and it is sized in such a way as to adequately handle the changes in calorific value. The combustion air system includes a primary air system with a total of 5 fans, three air/steam pre-heating exchangers with adjustable bypass for the air, and a secondary air system with 2 fans. All of the fans have speed adjustment with inverters, and the primary and secondary air flows for each zone and for each lane of the grate are automatically measured and adjusted. The primary air is blown in underneath the material through the cracks in the plates of the grate surface. In all, there are 5 air inlet zones, the first and last of which have 4 steps each, whereas the zones in the middle have 6 steps each. The rows of moving steps, totalling 13, are operated separately by two hydraulic cylinders installed on the sides. Every step of a single lane of the grate consists of two plates forming a joined chamber structure, built so that the cooling water can go through the steps and cool the metal surface of the grate. A fumes recirculation system is envisaged to control the combustion temperature and reduce the production of undesirable emissions, such as NOx. These fumes are withdrawn downstream of combustion fumes neutralisation. The combustion control system developed by the grate manufacturer provides better control and management via PLC. Ten hoppers connected to a wet collection system (Redler) are envisaged to remove the ash underneath the grate. The system transports and releases the material into the various zones to the waste extractor. Water also plays the role of a seal, preventing air from getting into the combustion system. The extractor is driven by two hydraulic cylinders connected to the main hydraulic station that controls the infeed system and grate system. 3. Waste storage prior to disposal or recovery at authorised plants The waste leaving the extractor of each furnace is conveyed on a vibrating table whose purpose is to uniform its flow, and from here to an iron removal system and then to the main conveyor belt that transfers it to the deposit area. Separated ferrous materials are accumulated in a storage ditch. The waste is stored in heaps inside the building where the deposit area is located, whereas special doors allow lorries to enter to load it and then transfer it to the recovery/disposal plant.
The back boilers installed on the two new lines are the natural circulation type, with cylindrical body placed at the top of the structure. They can produce 32.4 t/h of steam each. The exchange area consists of 4 vertical radiancy chambers and a horizontal convection channel containing the exchange banks. The saturated steam leaves the cylindrical body through several outlets that then flow into just one pipe connected to the inlet manifold of the superheater. The boiler is equipped with flat, insulated doors bolted to special frames so that the entire circuit of fumes and pipes can be thoroughly inspected. Hoppers for collecting ashes the fumes deposit during reversal of direction or that have detached during mechanical cleaning are underneath both the radiancy zone and the convective zone. The maximum slope is 35° so as to make unloading the ashes easy and sure. Furthermore, a flange interfaces the lower part with the clapets so they can be scavenged. 5. Gas treatment line A new, completely dry, gas treatment system has been designed for the two new lines (line 2 and line 3). Two reactor-filter systems installed downstream of the back boiler have been envisaged for each line, to then be followed by an ammonia-injection SCR system. Lime hydrate and activated carbon will be injected into the first reactor-filter system to reduce acids via salification, and dioxins, organic substances and volatile metals via adsorption. The salts and adsorbent carbon will then be blocked and collected in the bag filter and sent to the three residual calcic product storage silos by a pneumatic system. Sodium bicarbonate and, if necessary, activated carbon will be injected into the second reactor-filter system to reduce, by salification, residual acids that have not reacted with the lime and, by adsorption, dioxins, organic substances and residual volatile metals. This second stage will also considerably reduce SO2. The salts and adsorbent carbon, if any (hereinafter called residual sodic product), are blocked in the bag filter in this case as well, and sent to storage in a silo. A catalytic system with 24% ammonia solution (SCR) injected is envisaged downstream of the double filtration stage described above to reduce NOx, which also however contributes to reducing residual organic compounds, particularly the dioxins. The plant adopted in the project efficiently operates at low temperatures (no lower than 180°C) and ensures an annual mean concentration of NOx at the chimney lower than 100 mg/Nm3. The vaporized ammonia in the reactor is injected directly into the gaseous flow upstream of the catalytic converter, where the nitrogen oxides turn into molecular nitrogen and water.
The steam coming from the new lines (line 2 and line 3) is sent to just one turboalternator having a nominal electric power of 12.9 MW. Based on the season and needs, a part of the steam can be bled from the turbine to transfer heat energy by adjusted withdrawal to the district heating system through a dedicated heat exchanger. In the cogeneration layout, the turboalternator will be able to supply 8.4 MW of electric energy and 26 MW of heat energy. The steam leaving the turbogenerator is sent to an air condensation system. This system contemplates a geometric "saddle" configuration made up of four modules, arranged on two banks with two modules each.
B. MONITORING SYSTEMS
The two emissions points are monitored according to current regulations:
C. ENERGY SOURCES 1) Waste sources
The waste-to-energy plant is ISO 9001 and ISO 14001-certified, and attained EMAS registration in 2004. 2) Other sources Thermal energy system is completed by a thermal power station with 4 natural gas powered-boilers and 4 storage tanks, for the thermal energy daily-variability demand management.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
# |
Name of Example |
Location |
2 |
District Heating Alto Garda |
Riva del Garda, Trento |
|
The Initiative |
||||||||||||||||||||||||||||||||||||||
|
The DHC system at Riva del Garda in Trento Province, owned and managed by Alto Garda Servizi Teleriscaldamento (AGST) of the Alto Garda Servizi Group (AGS), will reduce annual energy consumption of Riva del Garda District (16.000 inhabitants) by about 6.700 toe, and decrease around 30% overall air emissions of the town and around 10% the CO2 emissions. The project initiated in September 2006, when AGS and Cartiere del Garda (local paper mill industry) constituted a new company, the Alto Garda Power with the mission to build and and manage a cogeneration power plant. In the meanwhile, the Alto Garda Servizi Teleriscaldamento company was constituted in order to design, built and manage the district heat grid. The construction od the CHP plant and of the heat distribution system started in June 2007 and the first customer was connected in october 2008. A relevant extension of the heat grid in Riva del Garda is planned in 2010; the possibility to deliver the heat up to Arco district (over 16.000 inhabitants, located at about 5 km) is also planned for the near future. The main technical data of the project are summarised in the following table: CHP Plant:
District Heating system
Heat grid management It should be noted that the heat distribution pipework is equipped with a continuous on-line monitoring sytem of the operating conditions and for the failures detection, thus greatly improving the reliability and the safety of the service. The system assures as well the automatic collection of the energy consumed by each substation. The utilization of recovery heat, and the high efficiency heat generation provided a valuable service to the customers, identified as follows:
Social and environmental benefits The DHC system in Riva del Garda allows an excellent synergy between a strong touristic vocation district and a modern industry mainly based on the utilisation of local resources. The consequent emission reduction resulting from DHC constitutes an important environmental element, particularly appreciated by the foreign tourists. Furthermore, the realization of the DHC system has been a key element for the refurbishing of the existing low efficiency cogeneration power plant, contributing to the economic and environmental sustainability of the local industry, which represents an important social element for the town. The realization of the initiative has beneficiated of a clear committment from the local authorities. The main obstacle, at the beginning of the project, was represented by the an uncertain potential customers acceptance. However, this problem has been overcome due to the good technical performances of the system and the good economic conditions offered for the delivery of the heat sevices. |